Does anyone have a macro or VBA code to list the properties of an mpp.

I review many schedules from different divisions of my company and it would
be very beneficial if I knew how the project was setup without going thru it
manually.

I'd like to have a report that will show me the settings of the project.
All the option settings.
All the custom fields in the project that have formulae and/or data.
Any comments in task notes.
Baseline set and interim baselines.
EVM technique used, %complete or Physical % Complete.
These are the one that come to mind immediately.

Can someone advise?

AnthemAz
 
J

Jack Dahlgren MVP

I have an example of reading project properties and checking task fields
here.

http://masamiki.com/project/macros.htm

Look for the "Check Fields" and "Write Properties" macros.

It would take a bit of coding to add in the other things and produce a
report but it is definitely possible.

-Jack Dahlgren
 