Does anyone have a macro or VBA code to list the properties of an mpp.
I review many schedules from different divisions of my company and it would
be very beneficial if I knew how the project was setup without going thru it
manually.
I'd like to have a report that will show me the settings of the project.
All the option settings.
All the custom fields in the project that have formulae and/or data.
Any comments in task notes.
Baseline set and interim baselines.
EVM technique used, %complete or Physical % Complete.
These are the one that come to mind immediately.
Can someone advise?
AnthemAz
I review many schedules from different divisions of my company and it would
be very beneficial if I knew how the project was setup without going thru it
manually.
I'd like to have a report that will show me the settings of the project.
All the option settings.
All the custom fields in the project that have formulae and/or data.
Any comments in task notes.
Baseline set and interim baselines.
EVM technique used, %complete or Physical % Complete.
These are the one that come to mind immediately.
Can someone advise?
AnthemAz