John R. Aldrin
Hi,
I have a task that is estimated to take 6 weeks. I want to set this task up
such that it either starts 8 weeks before a milestore or finishes 2 weeks
before the milestone.
Is there a way to do this w/o specifing a specific date?
The milestone's date is a result of dependent task durations and is not
hardcoded.
Thanx
jra