I am working as a planning engineer.I updated and track the schedule on
monthly basis. The main problem I face is basically MSP takes times based %
completion.which in no case a true indication of actual % completion of the
project.For other % completions like work and physical % completion it doesnt
give consolidated % completion or summerized % completion.So what is more
appropriate way of tracking?