K
ks2008
Please confirm my understanding, stated in the quote.
"When I complete my project I will not have schedule variance(sv), but
there could be some cost variance (cv). Because, when I complete the
project, there is no work left, yet to complete, however there is a
chance I would have incurred more expense than I planned so there will
be a cost variance."
BTW, Here is my question ?
I would have planned to complete on date X, but I really completed on
date Y.
a) What we call the days difference ie. ( Y - X ) days ?
Is it called Delay ?
b) What we call the Amount difference ie. $(Y-X)
ie. ( Actual BAC - Planned BAC )
thanks
KS
"When I complete my project I will not have schedule variance(sv), but
there could be some cost variance (cv). Because, when I complete the
project, there is no work left, yet to complete, however there is a
chance I would have incurred more expense than I planned so there will
be a cost variance."
BTW, Here is my question ?
I would have planned to complete on date X, but I really completed on
date Y.
a) What we call the days difference ie. ( Y - X ) days ?
Is it called Delay ?
b) What we call the Amount difference ie. $(Y-X)
ie. ( Actual BAC - Planned BAC )
thanks
KS