T
TroyS
I know that Actual Work applied will impact Scheduled Work, but i'm trying to
find a way to minimize the amount of changes and schedule updates that need
to be performed by PMs.
Here is the situation:
I have Ops Support tasks that occur throughout the year. I want and am
scheduling a Resource 4h per week on that task for the next 52 weeks.
If that person submits Actuals thru Timesheets say 3h for the week or 6h for
the week, the Work scheduled in the future week (say next week's planned
effort) is impacted.
Scheduled weekly: 4h, 4h, 4h (ie next 3 weeks)
Actual Weekly: 6h (Current Week), then Scheduled work is 2h, 4h (Next 2 Weeks)
but i don't want the scheduled work in the next 2 weeks to change
I've tried fixed units, fixed work and neither seem to do the trick. I don't
have any options turned (Tools - Options - Calculate) that should be grabbing
work from the subsequent week.
Any ideas would be helpful as I'm getting an earful from PMs. I suspect that
this is the nature of Microsoft Project and expect it, but no one wants to
hear that...
find a way to minimize the amount of changes and schedule updates that need
to be performed by PMs.
Here is the situation:
I have Ops Support tasks that occur throughout the year. I want and am
scheduling a Resource 4h per week on that task for the next 52 weeks.
If that person submits Actuals thru Timesheets say 3h for the week or 6h for
the week, the Work scheduled in the future week (say next week's planned
effort) is impacted.
Scheduled weekly: 4h, 4h, 4h (ie next 3 weeks)
Actual Weekly: 6h (Current Week), then Scheduled work is 2h, 4h (Next 2 Weeks)
but i don't want the scheduled work in the next 2 weeks to change
I've tried fixed units, fixed work and neither seem to do the trick. I don't
have any options turned (Tools - Options - Calculate) that should be grabbing
work from the subsequent week.
Any ideas would be helpful as I'm getting an earful from PMs. I suspect that
this is the nature of Microsoft Project and expect it, but no one wants to
hear that...