scheduled finish date changed after import

J

JennPenn07

Hello, I have PS2003 with SP3. I imported to project server a local copy
from my desktop and the scheduled finish date changes. What reasons could
this happen?
 
M

Marc Soester [MVP]

Jenn, when you import a schedule, the schedule generally uses the global
calendar which may be different to your local calendar. That could be one
reason.
Also when you map a local resource to a global resource and the global
resource has a different resource calendar than the original local resource,
that could be another reason.
Hope this helps
 
J

JennPenn07

yes, thanks

Marc Soester said:
Jenn, when you import a schedule, the schedule generally uses the global
calendar which may be different to your local calendar. That could be one
reason.
Also when you map a local resource to a global resource and the global
resource has a different resource calendar than the original local resource,
that could be another reason.
Hope this helps
 