R
renebeets
Hi,
I'm trying to create a Project that will over a few weeks and am coming up
with the following problems:-
1. Our standard working day is 7:30am to 11:30pm but I need to be able to
calculate overtime for hours outside of 8:00am to 5:00pm.
2. I need to be able to calculate an amount for Accommodation (per person
per day) of the contract running and would like this to be automatic so if my
duration increases then the amount for accommodation must change too
Most of my durations are calculated in hours but could run over 2 days with
multiple resources on each.
Any and all help is greatly appreciated!!!!
Thank you!!!
I'm trying to create a Project that will over a few weeks and am coming up
with the following problems:-
1. Our standard working day is 7:30am to 11:30pm but I need to be able to
calculate overtime for hours outside of 8:00am to 5:00pm.
2. I need to be able to calculate an amount for Accommodation (per person
per day) of the contract running and would like this to be automatic so if my
duration increases then the amount for accommodation must change too
Most of my durations are calculated in hours but could run over 2 days with
multiple resources on each.
Any and all help is greatly appreciated!!!!
Thank you!!!