Scheduled Variance

V

verossa

Hi All

Wouldn't the scheduled variance be better represented as a duration of time e.g. days, weeks, months etc. When I export the project this is represented as £ sterling. Or am I missing the point as usual

TIA
Vers
 
G

Gérard Ducouret

Hello Verossa,

The Schedule Variance is the difference between BCWP and BCWS which are
expressed in currency.
For ex: For the end of July, you expected to make a work amount which was
budgeted for 12000 £
At he end of july, you observe that the work done was budgeted for 10000 £ .
10000 £ was the value of the expected work for the end of June.
So you are 1 month late

Hope this helps,

Gérard Ducouret


verossa said:
Hi All,

Wouldn't the scheduled variance be better represented as a duration of
time e.g. days, weeks, months etc. When I export the project this is
represented as £ sterling. Or am I missing the point as usual.
 
J

JuileS

Hi Verossa,
Try viewing/exporting the variance table. It shows start
and finish variances in time durations not as a monentary
unit.
Hope this helps.
Julie
-----Original Message-----
Hi All,

Wouldn't the scheduled variance be better represented as
a duration of time e.g. days, weeks, months etc. When I
export the project this is represented as £ sterling.
Or am I missing the point as usual.
 
V

verossa

Hi Gerard

Hope you're well. Thanks for responding - it makes more sense now

Speak soon :-
Vers
 
J

JulieS

You are most welcome!
Julie
-----Original Message-----
Hi Julie,

Hpe you're well.

Thanks for the tip. I'll try it and see if I can
incorporate this into my project analysis.
 
M

Mark Durrenberger

Yes one of the funny things of EV is that schedule variance is expressed in
currency units
You can approximate a schedule variance in terms of duration units if you
divide the schedule variance by the burn rate (average dollars or pounds or
yen per day you are spending).

You can also project a new project duration using the SPI (schedule
performance index). Divide the original (baseline) duration by SPI.

Remember an SPI less than 1.0 means you are likely behind schedule and
greater than 1.0 means you are likely ahead of schedule.

An SPI of 0.9 means that for every 10 planned schedule days of work, you are
getting 9 schedule days of result.


Mark

--
_________________________________________________________
Mark Durrenberger, PMP
Principal, Oak Associates, Inc, www.oakinc.com
"Advancing the Theory and Practice of Project Management"
________________________________________________________

The nicest thing about NOT planning is that failure
comes as a complete surprise and is not preceded by
a period of worry and depression.

- Sir John Harvey-Jones
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top