Yes one of the funny things of EV is that schedule variance is expressed in
currency units
You can approximate a schedule variance in terms of duration units if you
divide the schedule variance by the burn rate (average dollars or pounds or
yen per day you are spending).
You can also project a new project duration using the SPI (schedule
performance index). Divide the original (baseline) duration by SPI.
Remember an SPI less than 1.0 means you are likely behind schedule and
greater than 1.0 means you are likely ahead of schedule.
An SPI of 0.9 means that for every 10 planned schedule days of work, you are
getting 9 schedule days of result.
Mark
--
_________________________________________________________
Mark Durrenberger, PMP
Principal, Oak Associates, Inc,
www.oakinc.com
"Advancing the Theory and Practice of Project Management"
________________________________________________________
The nicest thing about NOT planning is that failure
comes as a complete surprise and is not preceded by
a period of worry and depression.
- Sir John Harvey-Jones