R
Redbone
I am having a problem entering work times for construction schedules that
span midnight. I frequently need to schedule outages that the working times
are around the clock seven days a week. Typically this type of outage would
be worked in twelve hour shifts starting at 7:00 A.M. and ending at 7:00 P.M.
and 7:00 P.M. till 7:00 A.M. I keep getting messages like " the end of the
shift must be later than the start of the shift " I have the same trouble
with outages that require me to work only at night. These shifts would be
from 7:00 P.M. to 7:00 A.M. with no work during the day. Can someone give me
some examples of how to set this up?
span midnight. I frequently need to schedule outages that the working times
are around the clock seven days a week. Typically this type of outage would
be worked in twelve hour shifts starting at 7:00 A.M. and ending at 7:00 P.M.
and 7:00 P.M. till 7:00 A.M. I keep getting messages like " the end of the
shift must be later than the start of the shift " I have the same trouble
with outages that require me to work only at night. These shifts would be
from 7:00 P.M. to 7:00 A.M. with no work during the day. Can someone give me
some examples of how to set this up?