Hello sanmar,
So, if I understand you, you wish to have a task duration of 1 hour
but not have 1 hour of work for each of the 5 resources?
If you've set the max. units for the resources below 100% and wish
to assign all 5 resources at their max. units:
Remove all resources from the task.
Uncheck effort driven
Assign each of the 5 resources and project will, by default, assign
each resource at his or her max. units and calculate the work for
each resource based upon the formula
Work = Duration * assignment units.
The resources may still be overallocated if they are assigned to
other tasks which overlap in time with the 1 hour meeting, in which
case, you might use Resource Leveling to resolve the issue. I'd set
the priority of the meeting task to 1000 and level with the option
to allow splits and not allow adjustment of individual assignments.
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit
http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project