J
JROD
Here's my problem using Microsoft Project Pro 2003 and PWA:
I would like to schedule a task such as a team meeting who's duration
will be 1 year, but the task only occurs one day a week. I do not want
to use the Recurring Task option because that would create 52 separate
tasks - I only want one task where the work for each week would equal
1 hour.
Optimally, the solution will put one task in the user's task screen,
and the user would only be able to enter time for the day the task is
to occur on, all other days would be disabled.
Any help would be greatly appreciated!
I would like to schedule a task such as a team meeting who's duration
will be 1 year, but the task only occurs one day a week. I do not want
to use the Recurring Task option because that would create 52 separate
tasks - I only want one task where the work for each week would equal
1 hour.
Optimally, the solution will put one task in the user's task screen,
and the user would only be able to enter time for the day the task is
to occur on, all other days would be disabled.
Any help would be greatly appreciated!