C
Compass Rose
I am trying to create a Project template for an organization that runs an
annual event. The date of the event will vary from year to year. The tasks
that have to be performed prior to the event won't change from year to
year-only the dates that they will be performed. Most tasks have predecessors
which are other tasks, but some of the tasks have Start Dates that are
relative to the Event Date, some starting as much as 1 year prior to the
event. For example, Task 1 has a Start Date of 1 year prior to the event.
Task 2 has task 1 as a predecessor. Task 3 has task 2 as a predecessor, etc.
I would like the template to work in such a way that to produce the Gantt
chart for a year's event, the user would enter the Project End Date in the
Project Information and all the tasks will be adjusted accordingly.
How should the task predecessors and 'Schedule from' in the Project
Information be set up to achieve this?
TIA
David
annual event. The date of the event will vary from year to year. The tasks
that have to be performed prior to the event won't change from year to
year-only the dates that they will be performed. Most tasks have predecessors
which are other tasks, but some of the tasks have Start Dates that are
relative to the Event Date, some starting as much as 1 year prior to the
event. For example, Task 1 has a Start Date of 1 year prior to the event.
Task 2 has task 1 as a predecessor. Task 3 has task 2 as a predecessor, etc.
I would like the template to work in such a way that to produce the Gantt
chart for a year's event, the user would enter the Project End Date in the
Project Information and all the tasks will be adjusted accordingly.
How should the task predecessors and 'Schedule from' in the Project
Information be set up to achieve this?
TIA
David