R
Roy
I am the scheduling manager for a fairly large organization. We have a new
engineering and installation director that is insisting on having his people
develop their activities in our schedules as exactly 10 day work packages.
He says, if you have activities that are 2 day duration, combine them with
other short activities to get to 10 days. If you have a 15 day activity,
break it down into 2 activities and add shorter activities to come up to 10
days. We have complex schedules that typically span 2 years in duration. By
normal scheduling we have approximatley 2000 lines in a schedule and
individual tasks range from 1 day to 20 days (with manufactruing being an
exception of over 20 day durations). Since this directors personnel were
formerly scheduling to the activity level, they are having trouble
understanding having exactly 10 day work packages. We have talked with this
director about the fact that best practice states 20 hours to 80 hours for a
work package, but he says anything less that 2 weeks (80 hours) is too fine a
level to schedule to. I am wondering if anyone has attempted to schedule
this way and whether or not it can be successful.
engineering and installation director that is insisting on having his people
develop their activities in our schedules as exactly 10 day work packages.
He says, if you have activities that are 2 day duration, combine them with
other short activities to get to 10 days. If you have a 15 day activity,
break it down into 2 activities and add shorter activities to come up to 10
days. We have complex schedules that typically span 2 years in duration. By
normal scheduling we have approximatley 2000 lines in a schedule and
individual tasks range from 1 day to 20 days (with manufactruing being an
exception of over 20 day durations). Since this directors personnel were
formerly scheduling to the activity level, they are having trouble
understanding having exactly 10 day work packages. We have talked with this
director about the fact that best practice states 20 hours to 80 hours for a
work package, but he says anything less that 2 weeks (80 hours) is too fine a
level to schedule to. I am wondering if anyone has attempted to schedule
this way and whether or not it can be successful.