I
Ivivanti
Hi -
What's the best way to track the following scenario:
Let's say I have a list of tasks, each effort-driven, and each with an
estimated amount of Work. I'll use one task as an example:
Write test document 40 hours
When my team gives me hours and status updates I want them to give me the
times worked on each task AND the remaining hours for that task. So, let's
say the developer with the above task says they spent 32 hours on the task
this week and they have 16 hours left.
I don't want project to automatically take the 32 hours and say the task is
80% done. So, should I enter the 32 hours in the Actual Work column and 48
in the Work (planned) column?
Are there any global settings I should set to make this easier?
Thanks!
Ivi
What's the best way to track the following scenario:
Let's say I have a list of tasks, each effort-driven, and each with an
estimated amount of Work. I'll use one task as an example:
Write test document 40 hours
When my team gives me hours and status updates I want them to give me the
times worked on each task AND the remaining hours for that task. So, let's
say the developer with the above task says they spent 32 hours on the task
this week and they have 16 hours left.
I don't want project to automatically take the 32 hours and say the task is
80% done. So, should I enter the 32 hours in the Actual Work column and 48
in the Work (planned) column?
Are there any global settings I should set to make this easier?
Thanks!
Ivi