Ali B. said:
Hi John
Thank you for your fast reply. As you already found out, I mixed up work and
duration. But my problem still exists.
I don't agree that this is the only option. The other option would be to
increase the resource units of that task.
I tried to change the task type to 'fixed duration' (because the start and
the end are given), but it didn't help.
Isn't there any way to force project to change the resource units?
Thanks for any reply
Ali,
Sorry I forgot an apostrophe on the "its". What that sentence was saying
is that under Project's rules, Project's only option is to shift the
start date back by one day. Project is constrained to operate under a
strict protocol of rules and algorithms, however as users we of course
have many options, so yes, another option is to increase the resource
units - but that is the user's option not Project's. Remember you are
dealing with software, so what may be an "option" in your mind isn't
necessarily an option for the application. It is just the hard reality
of working with a computer application. What we think of a a logical
path isn't necessarily what the software will do - oh what we wouldn't
give for some fuzzy logic.
OK, enough philosophy. So how do you achieve what you want? Since you
changed the ground rules of the original task (i.e. you modified the
working time calendar, thereby effectively changing the task duration -
remember duration is working time). Setting the task up as fixed
duration doesn't help and we already know what Project does if the task
is fixed work. It's not hard to guess what Project will do if we try to
set the task to fixed units, after all, you don't want fixed units.
Here's what you can do. After you have changed the resource calendar,
Project will of course change the duration. Manually reset the duration
to 10 days. This will cause Project to up the work. So re-adjust the
work back to 40 hours. Then Project will increase the unit assignment
level to 56% - exactly what you want.
Although Project's work equation (i.e. duration = work/units) follows a
strict set of rules, there are user scenarios that do not always honor
the constraints of the work equation (i.e your scenario). In those
cases, the task parameters may need to be revised using additional steps
to create the desired result.
No one ever said that project management was easy nor that Project is an
easy application to learn and use. That's why we love it so much - it is
challenging to say the least.
Hope this helps.
John
Project MVP