I
iainjh
Hi all
I'm scheduling a game software development. Notwithstanding , or ignoring
inaccurate estimations for a moment, I'm assuming 3 weeks work and 1 week
contigency in each working month. Experience tells me that contingency is
about right over the space of a month due to slippage, change of spec or
other game dev 'issues' that happen, but this rarely works if applied right
down to individual task estimations or disciplines (of which there are many).
In the calendar I've set the last week of each month as nonworking to layout
the basic schedule.
Now I need to add [booked] vacation time for each resource, I find theres no
concept of multiple calendars or a way to book that resource 'out' when his
vacation overlaps on my of the contingency periods. project sees the calendar
is nonworking and so i cant book his holiday in.
How am I best to schedule contingency anmd holidays then? I have c. 40
reosources and i wanted to keep it simple.
thanks for advice and thoughts!
I'm scheduling a game software development. Notwithstanding , or ignoring
inaccurate estimations for a moment, I'm assuming 3 weeks work and 1 week
contigency in each working month. Experience tells me that contingency is
about right over the space of a month due to slippage, change of spec or
other game dev 'issues' that happen, but this rarely works if applied right
down to individual task estimations or disciplines (of which there are many).
In the calendar I've set the last week of each month as nonworking to layout
the basic schedule.
Now I need to add [booked] vacation time for each resource, I find theres no
concept of multiple calendars or a way to book that resource 'out' when his
vacation overlaps on my of the contingency periods. project sees the calendar
is nonworking and so i cant book his holiday in.
How am I best to schedule contingency anmd holidays then? I have c. 40
reosources and i wanted to keep it simple.
thanks for advice and thoughts!