T
TomR
I'm using Project 2007 with CA Clarity. I opened the project in Microsoft
Project and scheduled the project. The tasks where dates changed were
highlighted as expected. However, the dates and work effort for one task
along with the activities and phases it is part of continue to change each
time I hit F9. There were NO updates to the plan in between requests to
schedule yet the dates continue to change. Changes to the task type have no
effect on the behavior.
Project and scheduled the project. The tasks where dates changed were
highlighted as expected. However, the dates and work effort for one task
along with the activities and phases it is part of continue to change each
time I hit F9. There were NO updates to the plan in between requests to
schedule yet the dates continue to change. Changes to the task type have no
effect on the behavior.