T
Tom G.
What is the best way to schedule a series of activities from a fixed
finish date? We are planning an event that takes place on July 23, 2005. I
am trying to plug in things like:
Issue press release 3 days before event (must occur on)
Issue press release 30 days before event (could be +/- 3 days)
Design, print, mail brochures must be finished 60 days before event.*
* Design and print can happen early but mailing must
take place no earlier than 60 days before event and no
later than 45 days before event.
These activities needs to be relative days in case we have to reschedule
the entire event for a later date. However, most tasks MUST happen as
outlined above (finish x number of days before event).
I am fairly used to constructing projects that have regular SF relations
and the end date floats depending on the length of time. Here we're trying
to plan backwards and I'm not sure I'm doing what I want.
Thanks for the help!
finish date? We are planning an event that takes place on July 23, 2005. I
am trying to plug in things like:
Issue press release 3 days before event (must occur on)
Issue press release 30 days before event (could be +/- 3 days)
Design, print, mail brochures must be finished 60 days before event.*
* Design and print can happen early but mailing must
take place no earlier than 60 days before event and no
later than 45 days before event.
These activities needs to be relative days in case we have to reschedule
the entire event for a later date. However, most tasks MUST happen as
outlined above (finish x number of days before event).
I am fairly used to constructing projects that have regular SF relations
and the end date floats depending on the length of time. Here we're trying
to plan backwards and I'm not sure I'm doing what I want.
Thanks for the help!