AthleteTO
I've been banging my head against the wall long enough! Appreciate any help.
I have multiple tasks assigned to a resource, Dustin. Dustin is able to
commit a maximum of 14 hours (2 days) per week to the project - not on any
particular day. Likewise, I am committed for 3 days per week (21 hours) to
the project, and my time is flex time, as well - it will be different days
and times each week.
I have found that, no matter how I play with duration, work, and
percentages, the project plan that MS Project creates does not make sense.
Furthermore, it tries to schedule me even on days I have marked as
non-working days!!
Help - what's going on?
I have multiple tasks assigned to a resource, Dustin. Dustin is able to
commit a maximum of 14 hours (2 days) per week to the project - not on any
particular day. Likewise, I am committed for 3 days per week (21 hours) to
the project, and my time is flex time, as well - it will be different days
and times each week.
I have found that, no matter how I play with duration, work, and
percentages, the project plan that MS Project creates does not make sense.
Furthermore, it tries to schedule me even on days I have marked as
non-working days!!
Help - what's going on?