Scheduling Holidays or non-working days

D

Dale Howard [MVP]

Miles --

Do the following:

1. Launch Microsoft Project Professional and log into Project Server with
administrator permissions
2. Click Tools - Enterprise Options - Open Enterprise Global
3. Click Tools - Change Working Time
4. Enter your 2006 holidays on the appropriate calendar (probably the
Standard calendar)
5. Click OK when finished
6. Save and close the Enterprise Global file

Hope this helps.
 
M

Miles

Thanks! worked perfectly!

Dale Howard said:
Miles --

Do the following:

1. Launch Microsoft Project Professional and log into Project Server with
administrator permissions
2. Click Tools - Enterprise Options - Open Enterprise Global
3. Click Tools - Change Working Time
4. Enter your 2006 holidays on the appropriate calendar (probably the
Standard calendar)
5. Click OK when finished
6. Save and close the Enterprise Global file

Hope this helps.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top