E
Email Signatures
Very new to project and appreciate any help.
I have 28 tasks, each task is split into three sub tasks 2 x .5d and 1 x 2d
total for each task is 3d.
All 28 tasks start today but need to be completed by Dec14, what I want to
display is that each resource is allocated 3 days to work on an assigned task
but they can take any time upto the deadline of 14 Dec to carry out the work,
in esscence pick their own days.
Can this be done simply??
Many thanks
Kev
I have 28 tasks, each task is split into three sub tasks 2 x .5d and 1 x 2d
total for each task is 3d.
All 28 tasks start today but need to be completed by Dec14, what I want to
display is that each resource is allocated 3 days to work on an assigned task
but they can take any time upto the deadline of 14 Dec to carry out the work,
in esscence pick their own days.
Can this be done simply??
Many thanks
Kev