Scheduling on a nonworking day

L

Louise Anderson

Hello.
I am trying to schedule a task to begin on a Saturday, a nonworking day. I
know there is a setting that allows a PM to have the option to change the day
from a nonworking to a working day for that specific task. Where can I find
that setting?

Regards,
Louise
 
J

Jan De Messemaeker

Hi,

Tools, Change Working time, make a new calendar that has that Saturday or
any Saturday as working time
Now in Task Information, Advanced, in the Calendar window select that
calendar.
Hope this helps,
 