Glad to take a look at your file - my address is
sjhouse.remove.this@before_you_send_to_hotmail_dot_com after taking out
the obvious spam-thwarter text.
The "actuals" we are referring to are precisely what you are collecting
right now. What seems to missing from your equation is it sounds like
either you're not fully defining the project, including entering an
expected total duration of each task before the work begins, or you're
trying to use the "duration" field to hold the just remaining duration
rather than showing the sum of the work that has been done plus the work
that is remaining to do. Maybe I'm misunderstanding what you're doing,
and if I've not read between the lines correctly forgive me, but
remember that Project is first and foremost a planning tool and until
you have a plan that shows what you expect to do, when you expect to do
it, and how long you think it's going to take once you start it, you
really don't have anything to track work against.
I've been assuming you are familiar with the View, Tables menu option
that allows you to switch the Gantt chart table on the left side of the
screen between an Entry table that shows Duration, Start, and Finish
fields and a Tracking table that shows Actual Start, Actual Finish, %
Complete, Actual Duration, and Remaining Duration fields and also that
you are aware that those two tables are displaying totally different
series of data, albeit related data, about the tasks. The tracking
table does not contain the duration column that you see in the Gantt
chart entry table but you can add it if you like; personally I do like
to see it plus the scheduled Start and Finish fields as well, in
addition to the Actual Start and Actual Finish fields that are there by
default, so I usually add all 3 columns to the standard Tracking table
for convenience.
With the estimated total time known and the schedule showing the
expected start date, the only actuals you need for tracking are actual
start date and time actually worked expressed either in days or %
complete, and optionally the estimated time remaining if it looks like
the original duration estimate was off. Either enter actual start date
and percent complete or enter the actual start date, days worked and
days remaining in the tracking table. Let's say today is Friday. I've
got a task that was expected to take a total of 5 days and as of today
I'm told it is 60% done, 40% remaining if you prefer, thus it has 2 days
remaining. Was supposed to be done last week so the schedule currently
shows it was to start last Monday and end today. In the Tracking table
enter 60% complete. Project now shows an actual start of last Monday
(it assumes the scheduled start was the actual unless you tell it
otherwise in the Actual Start field) and 3 days of work has been done.
The Gantt chart task bar shows a solid bar inclusion covering Mon, Tues,
Wed while Thur and Fri show the original plain bar. In the menu select
Tools, Tracking, UpdateProject, RescheduleUncompletedWorkAfter and make
it the current date (or your reporting date) if it doesn't already show
it. If today is Fri, "after today" means that the earliest the 2
remaining days worth of work could start is next Monday. Project splits
the task bar, last Thur and Fri show as a dotted line in the bar, the
remaining part of the task bar now lays over next Mon and Tues, the
duration remains the same (5 days - the task took a holiday last Thur
and Fri so they don't count in the duration) but the new finish date is
now next Tue at 5pm instead of today at 5pm. Any tasks dependent on
that one now also move out in the schedule by 2 days, pushed back be the
delay in their predecessor.
Or I've got a task that originally was expected to take 10 days, I've
been told we worked 4 days on it this week and it looks like we'll be
finished in 2 more days, so we are not 50% done (5/10) but rather 83%
(5/6) done. In that case you enter an actual duration to date of 4 days
and a remaining duration of 2 days in the tracking table, Project
calculates the percentage for you and also sets the duration field to 6
days. The rest of the procedure is the same.
You CAN get to the minute by minute (well, hours per day is more
reasonable) level of detail if you like but it sounds like there's
really no need to do that in your case.