1. I have resources in PWA setup to work mon-fri. But when I schedule a task
for that resource it schedules the task through the weekend. I have checked
to see if the task was ignoring the resources calendar but it isn't. Why is
it schedule the task through the weekend. The project plan is set to use a
predefined calendar from Project Server that does not have weekends as
workdays.
2. If you do not usually work weekends but sometimes you have a task or 2
that need to work through the weekend. What is the best approach to solve
this problem.
for that resource it schedules the task through the weekend. I have checked
to see if the task was ignoring the resources calendar but it isn't. Why is
it schedule the task through the weekend. The project plan is set to use a
predefined calendar from Project Server that does not have weekends as
workdays.
2. If you do not usually work weekends but sometimes you have a task or 2
that need to work through the weekend. What is the best approach to solve
this problem.