Hello All-
I'm sure this is a very basic question, but I'm looking for
thoughts/suggestions/experience. When scheduling the availability of project
participants, I always schedule below 100% to account for the fact that
resources are rarely devoted to a project full time (and even when they are,
they have sick days, e-mail to check, etc). My question is about how I
should schedule project-related recurring activities that involve project
participants (such as a recurring project status meeting). Is that something
I should put in Project, or should I just reduce everyone's availability by
that amount of time? Any recommendations would be much appreciated. Thanks,
-Sean
I'm sure this is a very basic question, but I'm looking for
thoughts/suggestions/experience. When scheduling the availability of project
participants, I always schedule below 100% to account for the fact that
resources are rarely devoted to a project full time (and even when they are,
they have sick days, e-mail to check, etc). My question is about how I
should schedule project-related recurring activities that involve project
participants (such as a recurring project status meeting). Is that something
I should put in Project, or should I just reduce everyone's availability by
that amount of time? Any recommendations would be much appreciated. Thanks,
-Sean