Richard Millard
Hi,
When setting up a new project, I want to be able to setup the project so
that any resources assigned to it will assume that a full day of work on the
project is, for example, 4 hours. Each resource is available for 8 hours a
day of work (according to the resource calendar), but for this particular
project I only want each resource scheduled for a maximum of 4 hours.
Is it possible to do this so that if I assign a resource at 100% to a task,
the resource will only be scheduled for 4 hours of work for this project for
this one day?
Note: I am using Project Professional 2003 with Project Server.
Thank you,
Richard Millard
When setting up a new project, I want to be able to setup the project so
that any resources assigned to it will assume that a full day of work on the
project is, for example, 4 hours. Each resource is available for 8 hours a
day of work (according to the resource calendar), but for this particular
project I only want each resource scheduled for a maximum of 4 hours.
Is it possible to do this so that if I assign a resource at 100% to a task,
the resource will only be scheduled for 4 hours of work for this project for
this one day?
Note: I am using Project Professional 2003 with Project Server.
Thank you,
Richard Millard