Ange
Hi
Just a quick question. If you have 2 or more resources on a task, does
project assume that only 1 person is required to complete the task? I have
some tasks where multiple people are listed as resources as they all have to
approve a deliverable etc. Project is allowing these task to finish on a day
when one of the resources is on leave. Is there any way of preventing this as
it is giving unrealistic finish dates?
Thanks
Ange