i have a question on how i can setup a task so that it will span over 10
days worth of duration (eg we have a 10 day lead time for change request to
be reviewed. It takes about an hour to raise the change).
I still want to show the duration of 10 days. If i use the work and
duration columns sure it works but if you go into the resource usage view, it
spans the work out in effort over the whole duration. If i want the 1 hour
of work to be done on a particular day, how do i change this?
Thanks in advance
i have a question on how i can setup a task so that it will span over 10
days worth of duration (eg we have a 10 day lead time for change request to
be reviewed. It takes about an hour to raise the change).
I still want to show the duration of 10 days. If i use the work and
duration columns sure it works but if you go into the resource usage view, it
spans the work out in effort over the whole duration. If i want the 1 hour
of work to be done on a particular day, how do i change this?
Thanks in advance