S
Steve Adams, PMP
Hi,
I Eric Uyttewall's book "Dynamic Scheduling with MS Project 2003" he
suggests a process for updating schedules. Prior to accepting updates he
suggests changing all Task Types to Fixed Units.
His argument is that since Actual and Remaining Work are being collected
(via the Timesheet) a Fixed Work task would not be calculated correctly,
i.e., either Units or Duration would be recalculated, but which one?
What is typically desired when updating the schedule, he states, is that
Duration changes, Units remains constant and Work is updated via the Actual
and Remaining Work values in the timesheet.
I didn't see any information on setting the Task Types back to what they were.
What are your thoughts on this concept? Is anyone adopting such a best
practice?
Thanks!
I Eric Uyttewall's book "Dynamic Scheduling with MS Project 2003" he
suggests a process for updating schedules. Prior to accepting updates he
suggests changing all Task Types to Fixed Units.
His argument is that since Actual and Remaining Work are being collected
(via the Timesheet) a Fixed Work task would not be calculated correctly,
i.e., either Units or Duration would be recalculated, but which one?
What is typically desired when updating the schedule, he states, is that
Duration changes, Units remains constant and Work is updated via the Actual
and Remaining Work values in the timesheet.
I didn't see any information on setting the Task Types back to what they were.
What are your thoughts on this concept? Is anyone adopting such a best
practice?
Thanks!