Lene is correct, because it requires PM approval before any resource changes
are made to the project schedule. Hlowever, because a resource can adjust
actual hours and add additional hours needed (also must be approved by PM) it
in effect will reschedule the project. Therefore, the PM must be careful
when accepting updates and see the impact before applying them.
Kevin