Hi all
I'm using project 98 (tho it seems to be so hopelessly bug-ridden that I'm
looking at upgrading), and have some projects that - although complex - all
happen within a day. Can Project 98 handle this (it doesn't seem to), or
Project 2003?
I've changed the timescale to be hours and quarter-hours, but there doesn't
seem to be anyway of managing the tasks at anything less than day-scale. I
can't for example, say 'must start at 3.30pm'. The gant chart looks as
though it should work, but doesn't actually seem to offer any functionality
at hour/minute level.
Is that true, or am I just not seeing it?
best wishes
Pen
I'm using project 98 (tho it seems to be so hopelessly bug-ridden that I'm
looking at upgrading), and have some projects that - although complex - all
happen within a day. Can Project 98 handle this (it doesn't seem to), or
Project 2003?
I've changed the timescale to be hours and quarter-hours, but there doesn't
seem to be anyway of managing the tasks at anything less than day-scale. I
can't for example, say 'must start at 3.30pm'. The gant chart looks as
though it should work, but doesn't actually seem to offer any functionality
at hour/minute level.
Is that true, or am I just not seeing it?
best wishes
Pen