Thanks,
Conrad Santiago
----- Steve House wrote: -----
Putting in my 2 cents - a due date is not the same thing as a fixed date.
Yes, the dates that things are due are certainly fixed by contract, mandate,
etc very often. IMHO, one of the objectives in using a PMIS software
application like MS Project , though, is *not* to just put up a list of
deadlines in a convenient spot but rather to build a dynamic model of the
process that allows you to figure out just exactly what it is you have to
*do* in order to achieve those due dates. It answers the question "If I
sequence my tasks like this, and assign those resources to them is that
manner, will I or won't I finish on or before the due date?" That's why I
don't like to see many fixed dates in project plans - I want a plan that is
a tool that serves as a reality check, a reliable predictor of future
performance. To that end if the way I'm setting up tasks and assigning
resources so far is going to create a situation where I'll come in later
than my deadline, I want Project to red flag that by telling me what date I
really will hit if I try to work the plan as it's presently been conceived.
That's why I maintain that even though your due dates are fixed in granite,
your project plan's representation of those dates should not be - if they
are, MS Project will happily lie to you, telling you you'll be finishing
right on time when in fact it is absolutely impossible for you to do so with
the plan as presently structured. You'll feel happy right up until shortly
before deadline and then wonder why Project says you should be done yet
there's still 6 weeks of work left to do.
--
Steve House [MVP]
MS Project Trainer/Consultant
Visit
http://www.mvps.org/project/faqs.htm for the FAQs
Hmmm...these are interesting comments, Mark. You are making me
wonder if
we are using the right tool for our project scheduling purposes. Using MSP,
we are scheduling hundreds of projects a year. These projects have fixed
due dates (although, many do slide). However, I do see limitations in MSP
that would make my life easier. At times, I've felt using a white board to
layout the projects would be more effective for me to plan in the future. applications such
as
scheduling facilities (training rooms, testing labs) In general, the
attempts fail. I can't point to any one big reason they fail
but a
number
need to use
it a
lot.
Projects by nature have changes in dates. Training/Classes do
not
(once
scheduled they tend to stay put)
When you "fix" a date in project, all sorts of other strange
things
can
happen.
Training such as what you describe is a mix of "project" work and
non-project, repetitive work MSP does not handle the
non-project work
in an
for a
production
the "white
board"
calendar approach...
_________________________________________________________
Mark Durrenberger, PMP
Principal, Oak Associates, Inc,
www.oakinc.com
"Advancing the Theory and Practice of Project Management"
________________________________________________________
comes as a complete surprise and is not preceded by
a period of worry and depression.
wonder
what someone me familiar with Microsoft Project thinks of my chances... classes
that contain a number of exercises for each course. There are
tasks
that
must happen before each exercise and I am wondering if Project
is a
feasible
method to develop a way to track and plan for people, resource
use
and task