S
Saitei
I need some help on this one!!
I am trying to scan multiple timesheets in excel for a project code and then
capturing the hours worked for that project. I then need to have the hours
worked summed on a different work sheet to track hours worked for multiple
disciplines on one engineering project. (See below for example)
Example:
Timesheet 1:
Monday Tueday Wednesday
Thursday Friday
Project 'A' 4 2 8
0.5 0
Project 'B' 1 0 0
6.5 2.5
Project 'C' 3 6 0
1 5.5
Timesheet 2:
Monday Tueday Wednesday
Thursday Friday
Project 'A' 6 1 2
0.5 0
Project 'B' 1 1 0
6.5 2.5
Project 'C' 1 6 6
1 5.5
Tracking Sheet 3 :
(Total Hours worked by Project from timesheet 1 & 2)
Project 'A' 24
Project 'B' 21
Project 'C' 35
Any help on this would be greatly appreciated. Thanks in advance!!! 8^)
I am trying to scan multiple timesheets in excel for a project code and then
capturing the hours worked for that project. I then need to have the hours
worked summed on a different work sheet to track hours worked for multiple
disciplines on one engineering project. (See below for example)
Example:
Timesheet 1:
Monday Tueday Wednesday
Thursday Friday
Project 'A' 4 2 8
0.5 0
Project 'B' 1 0 0
6.5 2.5
Project 'C' 3 6 0
1 5.5
Timesheet 2:
Monday Tueday Wednesday
Thursday Friday
Project 'A' 6 1 2
0.5 0
Project 'B' 1 1 0
6.5 2.5
Project 'C' 1 6 6
1 5.5
Tracking Sheet 3 :
(Total Hours worked by Project from timesheet 1 & 2)
Project 'A' 24
Project 'B' 21
Project 'C' 35
Any help on this would be greatly appreciated. Thanks in advance!!! 8^)