K
Keoni
I have users who enter hours via PWA. Sometimes they go over the alloted
hours assigned to them to complete the task. PWA updates the hours
automatically instead of keeping the original hours. Is this normal? I know
you can see the original hours by going to options but is there a way to keep
it there without it automatically updating it? Also, how does a team member
get the hours to go back to the original hours if they added to many hours by
accident? For example task 1 is alloted 16 hours. Resource one puts in 18
over two days, which causes the total hours to be 18, and saves and updates
it. However, he realizes his error and was only suppose to enter in 16. So
when he updates his time to reflect 16 the time still stays as 18 and says
that the work is 93% complete when it should be 100% complete.
hours assigned to them to complete the task. PWA updates the hours
automatically instead of keeping the original hours. Is this normal? I know
you can see the original hours by going to options but is there a way to keep
it there without it automatically updating it? Also, how does a team member
get the hours to go back to the original hours if they added to many hours by
accident? For example task 1 is alloted 16 hours. Resource one puts in 18
over two days, which causes the total hours to be 18, and saves and updates
it. However, he realizes his error and was only suppose to enter in 16. So
when he updates his time to reflect 16 the time still stays as 18 and says
that the work is 93% complete when it should be 100% complete.