We have set up admin projects, based on the Admin template, for vacation
time, etc. I also have a customer enterprise project code with Admin as a
choice, as opposed to Maintenance or Enhancement projects, for instance. But
I can't get the projects based on the admin template to show up in a
portfolio view. I know the documentation says admin projects aren't
available in portfolio modeler. But Views? why can we see this time? thanks
 