B
BF2K
I appear to have discovered a bug in visual reports for consolidated projects.
(See thread in MS Projects general questions):
http://www.microsoft.com/office/com...4a9e-4da3-952b-8f0ff97343bc&lang=en&cr=US&p=1
I'm wondering if anyone has seen this problem, and/or might be able to
suggest a work-around using VBA. What I'm trying to do is get into excel the
time-phased resource loading for a consolidated project, showing at least the
level of effort assigned to a resource by each project in the master project.
.... The pivot table produced by Visual Reports would be perfect, except that
it produces incorrect data.
Thanks
(See thread in MS Projects general questions):
http://www.microsoft.com/office/com...4a9e-4da3-952b-8f0ff97343bc&lang=en&cr=US&p=1
I'm wondering if anyone has seen this problem, and/or might be able to
suggest a work-around using VBA. What I'm trying to do is get into excel the
time-phased resource loading for a consolidated project, showing at least the
level of effort assigned to a resource by each project in the master project.
.... The pivot table produced by Visual Reports would be perfect, except that
it produces incorrect data.
Thanks