J
Jurgen D
C2M/GRAFAN 20 20 25 0 days 1 day? Wed 14/04/04
Manufacturing 0 days 1 day? Wed 14/04/04
task1 0 days 1 day? Wed 14/04/04
task2 0 days 1 day? Wed 14/04/04
task3 0 days 1 day? Wed 14/04/04
This is a small project within ms project. Now i want to write a some
vba code to calculate something automatically. The following has to
happen: when i fill
in a number next to a task:
C2M/GRAFAN 15 10 25 0 days 1 day? Wed 14/04/04
Manufacturing 0 days 1 day? Wed 14/04/04
task1 5 0 days 1 day? Wed 14/04/04
task2 5 0 days 1 day? Wed 14/04/04
task3 5 0 days 1 day? Wed 14/04/04
The program has to take the sum of everything beneath 20, 20 or 25 and
then substract it from those figures. there for i have to select the
last level tasks but how can you specify in vba that you wan the last
leven or top level tasks. Can you use groups? or how should i do this?
Any help is welcome
Thanks
Manufacturing 0 days 1 day? Wed 14/04/04
task1 0 days 1 day? Wed 14/04/04
task2 0 days 1 day? Wed 14/04/04
task3 0 days 1 day? Wed 14/04/04
This is a small project within ms project. Now i want to write a some
vba code to calculate something automatically. The following has to
happen: when i fill
in a number next to a task:
C2M/GRAFAN 15 10 25 0 days 1 day? Wed 14/04/04
Manufacturing 0 days 1 day? Wed 14/04/04
task1 5 0 days 1 day? Wed 14/04/04
task2 5 0 days 1 day? Wed 14/04/04
task3 5 0 days 1 day? Wed 14/04/04
The program has to take the sum of everything beneath 20, 20 or 25 and
then substract it from those figures. there for i have to select the
last level tasks but how can you specify in vba that you wan the last
leven or top level tasks. Can you use groups? or how should i do this?
Any help is welcome
Thanks