J
John Sitka
Hi,
Split window
top = Gantt Chart
bottom = Resource Usage
When in the Gantt Chart view I highlight a set of tasks
Then with those same tasks highlighted which by the way come from
all the same resource, they show as a single resource set in the Resource
Usage
view. When the lower window has the focus I can
This allows a finer level of control of levelling or unlevelling resources
than seems to
be available using only one view as the driving control panel for how
leveling is to occur
That is I can't seem to level only a select set from the Gantt Chart view,
And I can't Clear the leveling from only a selected set in the Resource
Usage view.
So both need to be used together to get the desired behaviour which is
granular control
over how leveling is done.
Two questions
1.) is there a view that allows selective leveling/clearing from one window?
2.) does this seem like a possible candidate for a Macro that would change
the view, wait a little while
until Project Pro 2003 changes modes and then calls the relevent events thus
helping the usability. That is clears the leveling of
a certain selected set of tasks then re-levels those resources assigned to
those selected tasks?
Qualifier:
I tried to accomplish the same thing with various filters but wasn't having
much luck, could it be that proper RBS definitions would help
Thanks.
Split window
top = Gantt Chart
bottom = Resource Usage
When in the Gantt Chart view I highlight a set of tasks
Tools > Level Resources > Clear Levelling > Clear leveling ? for "Selected
Tasks" > YES
Then with those same tasks highlighted which by the way come from
all the same resource, they show as a single resource set in the Resource
Usage
view. When the lower window has the focus I can
Tools > Level Resources > Level Now > Level Now ? for "Selected Resources"
This allows a finer level of control of levelling or unlevelling resources
than seems to
be available using only one view as the driving control panel for how
leveling is to occur
That is I can't seem to level only a select set from the Gantt Chart view,
And I can't Clear the leveling from only a selected set in the Resource
Usage view.
So both need to be used together to get the desired behaviour which is
granular control
over how leveling is done.
Two questions
1.) is there a view that allows selective leveling/clearing from one window?
2.) does this seem like a possible candidate for a Macro that would change
the view, wait a little while
until Project Pro 2003 changes modes and then calls the relevent events thus
helping the usability. That is clears the leveling of
a certain selected set of tasks then re-levels those resources assigned to
those selected tasks?
Qualifier:
I tried to accomplish the same thing with various filters but wasn't having
much luck, could it be that proper RBS definitions would help
Thanks.