A
A Nony Mouse
Hi all.
I'm building a project that has a particular task requires 500 hours of
'effort' that recurs quarterly.
So, in project, I created a task and set it's duration to 500 hours. So
this task shows a start date and an end date roughly 20 days later.
My goal is to be able to assign additional people (resources) to the task to
'shorten' it. I've made some resources in Project and, I thought, assigned
them to the specific task. However, the tasks end date has not moved. My
guess would be that as soon as I assign more than one person, the tasks end
date should start 'sliding' earlier and earlier (by half with two people
assigned, by more with three, etc).
Anyone have any hints for what I'm doing wrong or where I can look to start
troubleshooting? Thank you very much!
I'm building a project that has a particular task requires 500 hours of
'effort' that recurs quarterly.
So, in project, I created a task and set it's duration to 500 hours. So
this task shows a start date and an end date roughly 20 days later.
My goal is to be able to assign additional people (resources) to the task to
'shorten' it. I've made some resources in Project and, I thought, assigned
them to the specific task. However, the tasks end date has not moved. My
guess would be that as soon as I assign more than one person, the tasks end
date should start 'sliding' earlier and earlier (by half with two people
assigned, by more with three, etc).
Anyone have any hints for what I'm doing wrong or where I can look to start
troubleshooting? Thank you very much!