Thanks Dale for your answer,
Actually, I don’t found any comments in the Approvals>Task Update area after
clicking on the task name link. So, I performed some extra tests:
- When the ProjectManager is not a ResourceManager no comments appear after
clicking on the name of the task in the Approvals>Task Update section. No
comment in the Approvals>Timesheet after clicking on the name of the task and
checking the “Transaction Comments and Task History†as well and even no
comments in the email notification received (even though there is a comment
area)
- When the timesheet has to be approved by a RM he do find the comment in
the Approvals>Task Update section. But nothing for the PM
- On the other side when the PM and the RM send a message after the
approval, the TeamMember can read it in My Task (“Transaction Comments and
Task Historyâ€)
So it seems for me that the PM never receives the comment from the TM when
the timesheet is auto-approved, or when it’s approved by a RM. I guess it
works only if the PM is also a RM.
When performing the tests, I found another potential problem. When the
timesheet has to be approved by a RM who is not the PM, it seems that the PM
received an email notification and has the ability to update his project
before the RM had approved the timesheet. Am I wrong?