J
Jennifer L.
Hi experts,
The project I'm working in is set to Fixed Duration, NOT Effort Driven. I am
trying to update my % complete (duration) and % work complete (work) columns
separately. I find that when there are no resources assigned to a task that I
am able to do this - update the progress (% complete), and the work (% work
complete) separately. For example, if a task is set to run for 4 days and
today is day 2, then the % complete will read 50%. And if on that same task I
know that though 50% of the duration has expired only 10% of the work is
actually complete, I can then adjust my % work complete column to read 10%.
The problem is, when I have resources assigned (and thus work assigned), if
I update the % complete and then try to adjust the % work complete, which
might be a different percentage, Project updates both as the same number.
Without adjusting my work or contouring my resources, is there a way to
separate the % complete and % work complete columns from updating as the same
percentage when resources are assigned to the task? If not, then I will just
create a custom field in which to insert the % work complete.
Thank you!
Jennifer
The project I'm working in is set to Fixed Duration, NOT Effort Driven. I am
trying to update my % complete (duration) and % work complete (work) columns
separately. I find that when there are no resources assigned to a task that I
am able to do this - update the progress (% complete), and the work (% work
complete) separately. For example, if a task is set to run for 4 days and
today is day 2, then the % complete will read 50%. And if on that same task I
know that though 50% of the duration has expired only 10% of the work is
actually complete, I can then adjust my % work complete column to read 10%.
The problem is, when I have resources assigned (and thus work assigned), if
I update the % complete and then try to adjust the % work complete, which
might be a different percentage, Project updates both as the same number.
Without adjusting my work or contouring my resources, is there a way to
separate the % complete and % work complete columns from updating as the same
percentage when resources are assigned to the task? If not, then I will just
create a custom field in which to insert the % work complete.
Thank you!
Jennifer