P
ProjectFly
I have what appears to be a simple problem. In my project plan, I have a mix
of internal resources and contractors. All of them have different rates.
I can very easily find the total cost for a task and nice rollup into
summary tasks etc. What I need is the separation of costs for internal and
external resources. I don't have any material costs. The output I am looking
for is as follows
Task Name Cost Internal External
Summary Task $450 $220 $130
Task 1 $100 $20 $80
Task 2 $150 $0 $150
Task3 $200 $200 $0
Thanks in advance for your help. I have tried adding a flag to resource
sheet to identify internal and external resources. How do I use this flag to
do the cost calculation. Are there any other simple ways of getting this
information.
of internal resources and contractors. All of them have different rates.
I can very easily find the total cost for a task and nice rollup into
summary tasks etc. What I need is the separation of costs for internal and
external resources. I don't have any material costs. The output I am looking
for is as follows
Task Name Cost Internal External
Summary Task $450 $220 $130
Task 1 $100 $20 $80
Task 2 $150 $0 $150
Task3 $200 $200 $0
Thanks in advance for your help. I have tried adding a flag to resource
sheet to identify internal and external resources. How do I use this flag to
do the cost calculation. Are there any other simple ways of getting this
information.