In a custom field, how do I format DateAdd("d",15,"2008/08/01") to display
the result in any one of Project's date formats instead of the serial date
39676 ? Project Help is no help on this one.
 
T

TonyK

Hi Andrew
You need to make sure you put the formula into one of Projects custom Date
fields. I tried it in the Date1 field and it worked fine.

Kind regards

Tony
 
A

andrew-k

Thanks, Tony
--
Best,
Andrew-K


TonyK said:
Hi Andrew
You need to make sure you put the formula into one of Projects custom Date
fields. I tried it in the Date1 field and it worked fine.