K
Konstantinos Christodoulakis
Dear all,
We are using Project Server 2007 in an organization of 500 users.
300 of them are using Timesheet Module of Project Server 2007 to complete
their actual work.
Planned work and task assignments per user are stored on Project Plans that
are stored on the Server.
Our Project Teams are working in 9 Big Scale Programs with a lot of tasks.
For Timesheet purposes we created 9 Project Plans with only the basic phases
of the projects.
So every Project Plan has almost 12 Task Lines and assignments per line.
Totally Tasks Lines are 9 * 12= 108 lines.
All these tasks have Start Date=01/01/2010 and End Date=31/12/2010.
For each task work from 1 to 30 users.
Timesheet tasks are prepopulated on Timesheet View.
As the preassigned tasks per user are so many, it takes at least 30 seconds
for the initials assignments to appear on the screen of the user.
In Fridays the workload is very heavy and we had a significant problem.
Even after loading the users have a significant problem, as the tasks are so
many and not grouped per Project, so they are scrolling up and down to
identify their task to fill in the actual hour.
QUESTIONS:
1. What is your proposal to increase the performance for this issue?
2. What should we change on configuration or architecture?
P.S.: I tested the loading of the same data on a Project Server 2010 and it
takes only 3 sec for the page to dispplay the tasks. 2007 takes more than 30
seconds, even if is in MOSS Farm Environment.
Best regards,
Konstantinos Christodoulakis
Project Manager
We are using Project Server 2007 in an organization of 500 users.
300 of them are using Timesheet Module of Project Server 2007 to complete
their actual work.
Planned work and task assignments per user are stored on Project Plans that
are stored on the Server.
Our Project Teams are working in 9 Big Scale Programs with a lot of tasks.
For Timesheet purposes we created 9 Project Plans with only the basic phases
of the projects.
So every Project Plan has almost 12 Task Lines and assignments per line.
Totally Tasks Lines are 9 * 12= 108 lines.
All these tasks have Start Date=01/01/2010 and End Date=31/12/2010.
For each task work from 1 to 30 users.
Timesheet tasks are prepopulated on Timesheet View.
As the preassigned tasks per user are so many, it takes at least 30 seconds
for the initials assignments to appear on the screen of the user.
In Fridays the workload is very heavy and we had a significant problem.
Even after loading the users have a significant problem, as the tasks are so
many and not grouped per Project, so they are scrolling up and down to
identify their task to fill in the actual hour.
QUESTIONS:
1. What is your proposal to increase the performance for this issue?
2. What should we change on configuration or architecture?
P.S.: I tested the loading of the same data on a Project Server 2010 and it
takes only 3 sec for the page to dispplay the tasks. 2007 takes more than 30
seconds, even if is in MOSS Farm Environment.
Best regards,
Konstantinos Christodoulakis
Project Manager