R
Rachel
We are using MS Project 2007 locally, we are not going to publish the
schedule. Initially I created the standard calendar in PWA and the project
adopted this schedule. I need to update the calendar and have done so PWA.
However, the local project is not adopting the changes. If I start a new
project, the new project has the updated holidays. How do I get the old
project to adopt the updated calendar? I've tried going to Tools / Change
Working Time and reselect the calendar, and it is still not working. Any
suggestions?
Thanks,
Rachel
schedule. Initially I created the standard calendar in PWA and the project
adopted this schedule. I need to update the calendar and have done so PWA.
However, the local project is not adopting the changes. If I start a new
project, the new project has the updated holidays. How do I get the old
project to adopt the updated calendar? I've tried going to Tools / Change
Working Time and reselect the calendar, and it is still not working. Any
suggestions?
Thanks,
Rachel