M
MSPLearner
This pertains to Project Server 2007 (Server & Client).
While our goal is to keep Server & Client SP & CU at the exact version
level, it is not always possible. Right now, I have plans to deploy
SP2+Aug09CU to both server & client (currently at SP1+Dec08CU).
The Server SP2+Aug09CU gets implemented one day followed by multiple waves
of client SP2+Aug09CU updates over 2-4 days (allowing for users traveling,
not connected to the network to receive client update). During this period,
it is possible that a Project Pro user with an older SP1+Dec08CU connects to
Project Server with SP2+Aug09CU. Is this OK? Or should this user be locked
out until his laptop is updated to SP2+Aug09CU? Is there is guidance / best
practice?
While our goal is to keep Server & Client SP & CU at the exact version
level, it is not always possible. Right now, I have plans to deploy
SP2+Aug09CU to both server & client (currently at SP1+Dec08CU).
The Server SP2+Aug09CU gets implemented one day followed by multiple waves
of client SP2+Aug09CU updates over 2-4 days (allowing for users traveling,
not connected to the network to receive client update). During this period,
it is possible that a Project Pro user with an older SP1+Dec08CU connects to
Project Server with SP2+Aug09CU. Is this OK? Or should this user be locked
out until his laptop is updated to SP2+Aug09CU? Is there is guidance / best
practice?