R
richecity
Hello all,
I have an interesting problem that is occuring when migrating to a different
server. We currently have 3 servers: development, acceptance test (AT), and
production. We migrate from development to AT and test all changes on AT;
finally, once everything has been tested we migrate from AT to production.
Recently we noticed that during migration, new calendars we being created on
the server we were migrating to. For example, if the development server had
2 calendars in its enterprise global, Standard and Acct Calendar, and prior
to migration, AT had the same two calendars, for some reason after the
migration AT would now have Standard and Acct Calendar1 (not Acct Calendar).
Also, on AT server all resources were assigned to Acct Calnedar prior to
migration, but after, they are now all assigned to the Standard Calendar. If
I open the organizer, the regular Acct Calendar has been deleted. We have
tried this several times and the same results occur. However, if we perform
the migration from development to AT with development having both calendars
and AT having only the Standard Calendar, the Acct Calendar shows up fine in
AT after the migration. Only problem with this is the resources that are on
AT need to have the Acct Calendar as their base caendar, so this poses a
problem since everytime we save it their it gets deleted. Any information on
this occurrence will be greatly appreciated.
Thanks
richecity
I have an interesting problem that is occuring when migrating to a different
server. We currently have 3 servers: development, acceptance test (AT), and
production. We migrate from development to AT and test all changes on AT;
finally, once everything has been tested we migrate from AT to production.
Recently we noticed that during migration, new calendars we being created on
the server we were migrating to. For example, if the development server had
2 calendars in its enterprise global, Standard and Acct Calendar, and prior
to migration, AT had the same two calendars, for some reason after the
migration AT would now have Standard and Acct Calendar1 (not Acct Calendar).
Also, on AT server all resources were assigned to Acct Calnedar prior to
migration, but after, they are now all assigned to the Standard Calendar. If
I open the organizer, the regular Acct Calendar has been deleted. We have
tried this several times and the same results occur. However, if we perform
the migration from development to AT with development having both calendars
and AT having only the Standard Calendar, the Acct Calendar shows up fine in
AT after the migration. Only problem with this is the resources that are on
AT need to have the Acct Calendar as their base caendar, so this poses a
problem since everytime we save it their it gets deleted. Any information on
this occurrence will be greatly appreciated.
Thanks
richecity