Service Pack 2a - Summary Tasks

B

Brian

In the documentation for SP2a, the description for issue 136 states: "The
resource manager or the project manager cannot distinguish between tasks."
Our assumption was that this referred to the absence of summary level tasks
on the "Approve Timesheets" and "View task changes submitted by resources"
pages.

We applied SP2a, and the summary level tasks are still not available on the
"Approve Timesheets" page nor on the "View task changes submitted by
resources" page. Have we done something wrong, or does this issue refer to a
problem other than the absence of summary level tasks on these pages?

Thanks,
Brian
 