Thank so much for all the information!
I suspect you were doing instead of setting task dependencies. Right?
Tasks that must follow one after another were linked. There are tasks
that go independent one from other, so they are not linked with lots of
tasks under them that are linked. The arrows I noticed about, where
those arrows, that show up when these independent tasks are linked to
deadline milestone. When one task is linked to another and so on, it
looks very readable, but when five tasks are linked to depending
deadline milestone, it looks quite arrowed..
"Best Practices"
suggest that A: Projects always have at least a Start milestone and a
Finish milestone; and B: all tasks have at least one predecessor and
at
least one successor. If nothing else is the predecessor, the start
milestone is the predecessor, and if nothing else is the successor,
the
finish milestone is.
This is a very good organization of a project. What to do, if there are
independent tasks? They all must be linked to the next big task, right?
You need to tell the software the
dependency relationship between all of the tasks in the project.
Otherwise,
how will the software know when things are supposed to be done?
My idea was that, if there are, for example, 10 big tasks that are not
linked one with another, but under them we have lots of small tasks that
are linked one with another within one of a grand tasks. Then, if it was
possible to set the deadline for the project and then if some of the 10
task wood go over the deadline date, then user would be noticed and user
would not need to create a deadline milestone for the project and link
all these 10 grand tasks to the end milestone, and no additional arrows
would appear. Some how I think that it might be possible for software to
control it. What do you think?
Thank you Paul!
Your idea will work, but in practice when you have some jobs done, some
jobs in the middle and some undone in the building site, then I think,
it will be hard, to count all deadlines from the end.. Or its just hard
for me.. But maybe I'll get used to it!!
At the moment I'm new to this program, and I'm trying to find the best
and simplest way, to coordinate and control things even not knowing what
this software is capable of, I fell, that it can do much. It would be
great to see someones mpp file, just to click it around, to see how
advanced it is possible to create adding all the workers, machinery etc.
Just discovered, that it is possible to add columns with user defined
formulas, I like it very much. I already have an idea, that I must make
one column that contains data of amount of job that must be done, second
column, that would contain the approximate amount of job that can be
done in one day, and the third column would calculate how much days are
needed for this work to be done by dividing first column by the second..
What do you think about this idea? Other vice I have never organized
things, and I think its not even possible to guess how much time it
would take..
So I'm widely opened for any ideas that could help me
better in my new job and it would be greatly appreciated.