M
Mark Byington
Suppose Resource 'A' is normal a part time resource and is set as 50% Max
Units in the EPM Resource Pool.
However, for a particular Project, they will be a 100% resource. Is there a
way to set their max units at 100% for the entire project? Setting MAX Units
at 100% on the Resource Sheet View will only work for that session...it needs
to be re-set each time the project is opened in Project Professional.
Also, if the resource wants to create a task for themselves using PWA, it
brings them in a the default % on the Resource Pool. Any way to change that?
Thanks...
Units in the EPM Resource Pool.
However, for a particular Project, they will be a 100% resource. Is there a
way to set their max units at 100% for the entire project? Setting MAX Units
at 100% on the Resource Sheet View will only work for that session...it needs
to be re-set each time the project is opened in Project Professional.
Also, if the resource wants to create a task for themselves using PWA, it
brings them in a the default % on the Resource Pool. Any way to change that?
Thanks...